The client had a non-compliant chemical tank farm that supplied their key central processing area. This had to be decommissioned and removed but only after the new system was installed, commissioned and tested. The new system comprised of a new 29m3 bulk caustic tank in a recently installed tank farm and drawing out bulk Nitric Acid and Sodium Hypochlorite tanks, with a 200m run along a pipe-bridge.
Other aspects to the job included the design and installation of:
Project Value: $1.3 Million
Duration: 12 Months
Project Type: Fixed Price (mechanical, electrical, automation and commissioning). Health & Safety managed under the client's Safe Work System
Consultant: N/A
Construction man hours: 9,000
Key Points:
Outcome:
Delivered safely
Delivered in budget
Delivered on time
Established new standard for IBC chemicals